Reporting a complex engineering program with a few KPIs and a stoplight chart

Suppose a director has ten programs to review in an hour, about six minutes each. In that time they need to learn three things: whether the program will meet its commitments, which way it is moving, and whether they have to decide something this week. The engineering behind a radar or a sensor array does not fit in six minutes, so somebody has to compress it, and the person who understands the engineering is usually the right one to do it.

I learned this on radar and RF hardware programs and again on capacitive sensor design for robotic sensing in commercial applications. The method I learned was to report each program through three to five measures tied to its goals, each with a red, yellow, or green status, reviewed every week or two. Picking those measures and their thresholds takes technical judgment. A measure leadership can act on has to follow the requirement that matters, move early enough to allow a correction, and have a threshold set with some knowledge of its noise.

This post covers how to choose the measures, a worked scorecard for a hypothetical radar program, how to set the thresholds, and the ways stoplight reports fail. The two main public cases are the review board report on the National Aeronautics and Space Administration (NASA) Psyche mission and a Government Accountability Office (GAO) audit of a federal stoplight dashboard.

What the scorecard has to answer

Each line on the scorecard covers one measure. A line that shows only the current value against target gives a snapshot, and a snapshot can look fine while the program drifts. Adding the recent trend and a flag for any decision needed lets a reader spend their six minutes on the right program.

A scorecard is lossy compression of the program’s state. In rate-distortion terms (the trade between how much information you keep and how much error you accept), the distortion to minimize is the cost of a wrong decision, meaning a choice leadership would have made differently with the full technical picture. The analogy gives a test for each candidate measure. A measure belongs on the scorecard if a plausible change in its value would change a decision above the program level.

The number three to five is a heuristic. A Project Management Institute (PMI) Global Congress paper by Kristine Hayes Munson recommends three to five key performance indicators (KPIs) per project and treats the exact count as a judgment call that depends on scope and complexity. GAO’s guidance on performance measures says good measures are “limited to the vital few.” Neither source tests the number against program outcomes, and I have not found a study that does.

The Columbia accident shows what compression costs when it drops the wrong detail. After foam struck the shuttle’s wing at launch in January 2003, a Boeing briefing slide on the debris analysis carried the title “Review of Test Data Indicates Conservatism.” Only the bottom of the slide noted that one estimate of the debris was 640 times larger than the data used to calibrate the model, and later analysis put it at 400 times (Columbia Accident Investigation Board (CAIB) report, Vol. I, p. 191). The board called “the endemic use of PowerPoint briefing slides instead of technical papers” an illustration of NASA’s problematic methods of technical communication (CAIB report, Vol. I, p. 191).

Start from the requirements and work down

A scorecard is easiest to build top-down, in three levels. The top is the program’s purpose: the mission or business outcome and the requirements that define success. The middle is the scorecard itself, three to five measures that predict whether the top will be met. The bottom is the technical evidence: test data, analyses, models, defect logs, and the dozens of engineering metrics a team tracks day to day. Each scorecard line should trace up to a requirement someone cares about and down to evidence a reviewer can inspect.

The NASA Systems Engineering Handbook describes the same structure. Its principles for technical assessment include “Use an agreed-upon set of well-defined technical measures,” “Report these technical measures in a consistent format at all project levels,” keeping historical data “for both trend identification and cross-project analyses,” and “Summarize the condition of the project by using color-coded (red, yellow, and green) alert zones for all technical measures” (NASA SE Handbook, §6.7, p. 159). The results feed the handbook’s decision analysis process. Major reviews such as the preliminary design review (PDR) and critical design review (CDR), along with routine status reviews, are the points where measures and their trends “should be carefully scrutinized for early warning signs.”

Most of the middle level comes from technical performance measures (TPMs), which track a parameter tied to a critical requirement against a planned value over time. The Department of Defense (DoD) Systems Engineering Guidebook says “Each measure or metric should have threshold, margin, and contingency values” (p. 10), and that TPM reporting “should be in terms of actual versus planned progress, plotted as a function of time and aligned with key points in the program schedule” (p. 109). As a best practice, the same guidebook asks programs to select and report at least 15 TPMs and metrics, collected monthly and reported to senior leadership at least quarterly (p. 10). A weekly scorecard sits on top of a set like that. It picks the few TPMs and programmatic measures closest to the program’s risks and points into the rest.

Two habits improve the selection, and the first is to prefer measures of progress over measures of activity:

Activity measureProgress measure
Tests runRequirements verified to their acceptance criteria
Defects closedOpen defects that block a requirement
Engineering hours spentForecast date for the next milestone against its baseline

Activity counts are easy to collect and almost always go up, which makes them poor evidence that a program will finish. The second habit is to pair each measure with one that pulls the other way. Andy Grove’s High Output Management (1983) recommends pairing indicators so that a measure and its counter-effect are both watched, such as inventory with shortages. The DevOps Research and Assessment (DORA) program’s metrics guide recommends “multiple metrics, including some with a healthy amount of tension between them.” A schedule measure needs a technical acceptance measure beside it, and a cost measure needs a performance measure.

Each measure also needs an operational definition before its first report: the numerator, the denominator, the data source, the owner, the target, and the yellow and red thresholds. A count of verified requirements means little until the team agrees what “verified” requires and whether deferred requirements leave the denominator.

A scorecard for a hypothetical radar program

The table below is a scorecard for an invented phased-array radar program in week 14 of a 26-week run to its critical design review. The numbers are chosen to illustrate the points that follow and do not come from a real program. The rows are a TPM for effective isotropic radiated power (EIRP) at the edge of scan, prime power against its allocation, design requirements verified by analysis and engineering-model tests against the verification plan, and the forecast date for CDR. Each row shows the last four weekly values, so the trend sits next to the color.

MeasureTarget and thresholdsLast four reviewsStatus
EIRP margin at 60° scan (TPM)≥1.0 dB above requirement; yellow 0–1.0 dB; red below 0 dB1.7, 1.6, 1.6, 1.6 dBGreen, flat
Prime power, 450 W allocation≥10% reserve; yellow 2–10%; red below 2%419, 423, 427, 431 WYellow, worsening
Design requirements verified vs plan≥95% of plan; yellow 85–95%; red below 85%31, 36, 41, 46 of 120 (plan: 49, 52, 55, 58)Red, improving
CDR forecast vs baselineOn time; yellow 1–10 working days late; red above 103, 5, 7, 9 working days lateYellow, worsening

Overall: red. EIRP margin is stable at 1.6 dB above its requirement. Verification is 12 requirements behind plan and closing the gap by 2 a week. Prime power reserve is 4.2% and shrinking by about 1 percentage point a week, and the CDR forecast is 9 working days late and slipping by 2 days a week.

Decision needed: yes. The antenna test range is behind both the verification gap and the CDR slip. Approve a second range shift for three weeks, or rebaseline CDR about seven weeks later, where the current slip rate puts it (9 working days now, 2 more a week, 12 weeks to go). The power trend stays with the team for now: the transmit/receive (T/R) module lead is running a bias-point trade study, due at the next review.

The scorecard follows four rules:

A status threshold is a detection threshold

A weekly value on a scorecard is a noisy estimate. An EIRP margin comes from a model fed with measured element patterns and component data that change as parts arrive, and a schedule forecast moves with every task update. Setting a yellow threshold on that value is the same problem as setting a detection threshold on a radar return. Set it close to the typical value and noise alone trips it. Set it far away and a real decline crosses it late.

Radar engineers set this threshold on purpose, with a constant false alarm rate (CFAR) detector that estimates the noise around each range cell and places the threshold to hold the false-alarm probability at a chosen value. A capacitive sensor designer makes the same trade between false triggers and missed events. A status threshold deserves the same treatment, with an estimate of how much the measure moves from week to week behind it.

The cost of a careless threshold is easy to compute under textbook assumptions: Gaussian noise, independent reviews, and a stable mean. A threshold 1 standard deviation (σ) below the mean turns yellow on noise alone in 15.9% of reviews, about 8 false yellows a year at a weekly cadence. At 2σ the rate falls to 2.3%, about 1 a year, and at 3σ to 0.13%. Real program data are often autocorrelated, meaning one week’s error is correlated with the next. If σ is the long-run standard deviation of the measure, the average rate stays the same, but false yellows arrive in runs of consecutive weeks. A leadership team that sees eight false yellows a year learns to discount yellow, and the real one gets the same discount. Panel (b) of the figure plots the rate for weekly and biweekly reviews.

Two-panel chart of synthetic data. Left panel: weekly margin above requirement in decibels over 12 reviews, with a dashed gray line marking the 1.0 dB yellow threshold and the region below it shaded light yellow. A blue stable series hovers between 1.5 and 1.7 dB. An orange falling series holds near 2.6 dB for six weeks, then drops about 0.16 dB per week to 1.6 dB at week 12, where both series meet. A dotted orange extension of the falling series reaches the 1.0 dB threshold near week 16. Right panel: false yellows per year from noise alone on a log scale against threshold distance below the mean in standard deviations, from 0.5 to 3. The weekly-review curve passes through 8.3 per year at 1 sigma and 1.2 per year at 2 sigma; the biweekly-review curve sits at half those values.

Synthetic data. (a) Two weekly margin series that both read 1.6 dB, and green, at week 12. The falling series’ six-week trend reaches the 1.0 dB yellow threshold near week 16. (b) Expected false yellows per year from noise alone, for a threshold placed a given number of standard deviations below a stable mean, assuming Gaussian noise and independent reviews. Generated by scripts/stoplight_trend_figure.py.

Statistical process control has a tool for this problem. Process behavior charts (Donald Wheeler’s term for Shewhart control charts) “separate the routine variation of the Common Causes from the exceptional variation of the Assignable Causes” (Wheeler, 2010), using limits computed from the data itself. The DoD guidebook lists a related attribute of a good TPM, a curve of planned “control limits or threshold values over time” used to judge “if the measure is in control” (p. 109). Hospital board reports are one place where the use of such limits has been measured. Schmidtke and colleagues found that of 1,488 charts in the board papers of 30 English National Health Service (NHS) trusts, only 88 (6%) depicted the role of chance (BMJ Quality & Safety, 2017). A paper in the same journal issue is titled “The problem with red, amber, green: the need to avoid distraction by random variation in organisational performance measures” (Anhøj and Hellesøe, 2017).

A threshold also misses the trend. Panel (a) shows two synthetic margin series that both read 1.6 dB and green at week 12. One holds steady while the other has fallen about 0.16 dB a week for six weeks, on a trend that reaches the 1.0 dB yellow threshold near week 16. The stoplight shows the same color for both, which is why each row of the example scorecard carries its last four values. A short series beside the color lets a reader see the slope without a statistics lesson.

A procedure follows from this. Take the red threshold from the requirement or commitment itself, and set the yellow threshold at the point where the team still has room to recover. Then check the yellow threshold against the measure’s standard deviation over several months of values. An estimate of σ from 10 weekly values carries a standard error of about 24%, so treat it as rough. If the threshold sits within about 1σ of the typical value, there are two remedies, and both cost something. Widening the band takes room away from recovery. Smoothing the measure with a three-week moving average cuts the noise by up to a factor of 1.7 when weekly errors are independent, and it adds about one review of lag.

Roll up by the worst case

The NASA handbook also says to “Encourage a logical process of rolling up technical measures,” and any program with more than a few subsystems has to roll measures up. The roll-up is also where status gets lost. Averaging has the problem I described for aggregate scores in failure taxonomies for ML and decision systems. An aggregate is a mixture over its parts, and it can move for reasons the aggregate itself cannot show.

NASA’s Psyche asteroid mission missed its 2022 launch period. The independent review board’s November 2022 report named late delivery of the guidance, navigation, and control (GNC) software and immature system testbeds as the proximate causes (p. 14). It also found that “Project schedule and progress-tracking metrics masked true development status,” and that the GNC software, the testbeds, and the verification and validation (V&V) effort “were never properly represented in either the Integrated Master Schedule or the progress metrics” (p. 26). On status colors, it found: “Risk assessments did not accurately communicate project health (i.e., many yellow risks, no red risks). Based on interviews, there was an aversion to ‘going red’ by project management.” Elsewhere in the report, the board recommended that “red scores should never be aggregated with green and yellow to obscure the severity of a red score” (p. 29). NASA’s response committed to a reporting format that “will not allow metrics to be rolled up in a way that conceals lower-level deficiencies or measurements against a moving plan.”

Shortcomings in programmatic metrics were one item in the board’s list of issues, and it called an imbalance between workload and staff a root cause. The metrics finding covers one problem among several, and it still shows how a reporting system can look orderly while failing to tell management what it needed to know. Psyche launched on a Falcon Heavy on October 13, 2023.

Three rules follow. The overall status of a program is the status of its worst row. A red at any level stays visible at the top until it is fixed or someone with the authority to do so accepts the risk. A lower-level measure that is missing from the roll-up counts as a gap in the report.

Gray means no current evidence

A federal dashboard shows what happens when ratings go stale. The IT Dashboard publishes a chief information officer (CIO) risk rating for each major federal information technology (IT) investment on a five-point scale, displayed as red (high and moderately high risk), yellow (medium), or green (moderately low and low). In a 2016 report, GAO compared its own assessments of 95 investments with the CIO ratings. Its assessments “matched the CIO ratings 22 times, showed more risk 60 times, and showed less risk 13 times,” and “Forty of the 95 CIO ratings were not updated during the month GAO reviewed” (GAO-16-494). GAO also wrote that ratings that leave out active risks “increase the chance that ratings overstate the likelihood of investment success.”

Forty stale ratings out of 95 point to a fourth status that most stoplight schemes leave out. The table gives four definitions, including gray:

StatusMeaning
GreenThe measure and its forecast are inside agreed tolerances.
YellowThe measure is outside tolerance or forecast to leave it, and the team has a recovery plan with an owner and a date.
RedA requirement, milestone, or constraint is breached or forecast to be missed, and the plan has to change.
GrayThere is no current, validated measurement, including any value that is missing or out of date.

I made the same choice in software. The verification runner in sysml2kit, my open-source tool for checking Systems Modeling Language (SysML) v2 requirements against analysis results, reports pass, fail, or unknown. Unknown on a must-severity requirement fails the run, “because a check that silently checked nothing is worse than a failure.”

Severity and escalation are separate questions, so they belong in separate fields. A red row can sit entirely within the team’s authority to fix, and a yellow row can need a decision only a director can make, such as a test-facility conflict with another program. A “decision needed: yes/no” field next to the status keeps a review from treating every red as a request for help and every yellow as no request at all.

Bad news has to be safe to report

Psyche’s “aversion to ‘going red’” matches a documented pattern. Snow and Keil built a model of software project status reporting that “uses discrete project status from traffic light reporting,” with inputs elicited from a panel of five experts. Its results indicated “that project managers are overly optimistic in their perceptions, and that executives receive status reports very different from reality,” and the authors concluded that “executives should be skeptical of favorable status reports” (Snow and Keil, 2002). Because it is a model, the size of the distortion depends on its inputs. A survey of 561 project managers by Iacovou, Thompson, and Smith found that optimistic biasing lowered reporting quality, and found “a positive effect of reporting quality on project performance” (MIS Quarterly, 2009).

Much of the fix is in how leadership responds. Amy Edmondson’s study of 51 work teams in a manufacturing company found that team psychological safety was associated with learning behavior, such as discussing errors (Edmondson, 1999). The design was cross-sectional, so it shows an association. In status terms, a team that reports red early should get help, and the scrutiny should go to a status that stayed green until the week it went red. Accountability still applies to inaccurate reports and to recovery plans that fail.

The other risk is that the scorecard becomes a target. Campbell’s law puts it this way: “The more any quantitative social indicator is used for social decision-making, the more subject it will be to corruption pressures and the more apt it will be to distort and corrupt the social processes it is intended to monitor” (Campbell, 1979). Goodhart’s law states the same problem for economic indicators, as an editorial by Mattson and colleagues discusses. A public example is the 2014 Department of Veterans Affairs (VA) wait-time scandal, where the VA Office of Inspector General (OIG) reported that “Thirty staff stated they used the wrong desired date of care, resulting in appointments showing a false 0-day wait time” (VA OIG, 2014). A program scorecard tied to individual performance reviews invites the same behavior on a smaller scale, which is one more reason to pair each measure with one that pulls against it.

Exploratory work needs evidence milestones

Everything above assumes the work has requirements and a plan to measure against. Exploratory research often has neither. A research team can make real progress by showing that a proposed architecture cannot work, and a percent-complete measure on that kind of effort reports a precision nobody has. For research, the scorecard can carry evidence milestones instead: the critical hypotheses, the experiment that will decide each one, the date it is expected to run, and the go/no-go decision it feeds. Status then shows whether the uncertainty is shrinking on schedule, and red means a decisive experiment has slipped or returned an answer that changes the plan.

Summary of the method

A program scorecard for leadership needs three to five measures, each traced to a requirement and defined before its first report. Every row carries a value, a target, a short trend, and a status, and the overall status is the worst row. Thresholds come from the requirement and the recovery margin, checked against the measure’s noise: a yellow threshold 1σ below a stable mean produces about 8 false yellows a year at a weekly cadence, and one at 2σ produces about 1. Missing data is gray. A separate field says whether leadership needs to decide something, and what.

Choosing the rows that predict the outcome, and thresholds that separate a trend from noise, uses the same knowledge as the engineering itself. That is why the technical lead should own the scorecard.

This is a personal reflection written on my own time, drawing on the public sources cited above. The views are my own and do not represent any current or former employer.

Frequently asked questions

How many KPIs should an engineering program report to leadership?

Three to five is a common practitioner heuristic for a weekly or biweekly executive view, and GAO's guidance says good performance measures are limited to the vital few. No study I have found tests the exact number. The executive measures sit on top of a larger engineering set: as a best practice, the DoD Systems Engineering Guidebook asks programs to select and report at least 15 technical performance measures and metrics.

What should red, yellow, and green mean on a program status report?

Green: the measure and its forecast are inside agreed tolerances. Yellow: the measure is outside tolerance or forecast to leave it, and the team has a recovery plan with an owner and a date. Red: a requirement, milestone, or constraint is breached or forecast to be missed, and the plan has to change. Add gray for a measure with no current, validated data, and record in a separate field whether leadership needs to make a decision.

Why do stoplight charts mislead?

A single color discards the trend and the noise. A measure that has been falling for six weeks can show the same green as a stable one, and a threshold set 1 standard deviation below a stable mean turns yellow on noise alone in about 16% of reviews. Averaging statuses also hides a single red. NASA's Psyche review board found many yellow risks, no red risks, and an aversion to going red.

What is a technical performance measure (TPM)?

A TPM tracks a technical parameter tied to a critical requirement, such as effective isotropic radiated power or prime power, against a planned value over time. DoD guidance says each one should have threshold, margin, and contingency values and asks for actual against planned progress plotted over time and aligned with the technical reviews.